The Challenge

Based in Herefordshire, an international cider producer was in the process of expanding their production facility. They required the professional electrical installation of an advanced central mains and LV distribution system alongside LED lighting, cable containment, control system wiring, and control panel connections.

The project required a fast turnaround from quotation to the onsite deployment of engineers, working alongside the building contractor prior to the full completion of the building ensuring all timelines were maintained and the project was delivered as per the schedule. With an aggressive time plan in place, a mixture of internal and external activities, and a fully operational production facility to contend with, we knew this would be a challenge worth taking on.

The Solution

Once awarded the project, Elmleigh agreed site-specific standards with the client and external contractors, over and above the industry regulations, before getting to work. Working closely with external contractors also onsite, we ensured all bespoke elements of the electrical installation fit with the client’s needs, keeping standards high across all aspects of design and installation.

Our highly skilled engineers who understand the importance of quality and thrive on meticulous planning were deployed to deliver a mix of bespoke stainless-steel constructed cable management and standard galvanised components to fit the installation requirement.

We also installed a full mains distribution system, a purpose-made central LV distribution system, cabled out to remote areas of the factory for sub-distribution, before moving onto the plant and machinery element – testing all of our core skills and showcasing our ability to deliver a full turnkey solution.

The electrical installation also required a mixture of standard galvanised ladder racking as well as bespoke stainless-steel constructed cable management.

The Outcome

With parts of the project still underway, it’s still early days to comment on the plant and machinery side of things, however, keep an eye out for updates on this exciting project expected to finish in May 2021! So far, the client has been extremely happy with the professionalism of our team and our ability to work quickly and efficiently within an operational site.

If you’re a business looking for a full, turnkey electrical installation solution, we’d love to help. Contact us today to discuss your project in more detail.

 

(18037 &17867)

Value £600k
Client Cider Manufacturer
Location Herefordshire
Time March - April 2021

More Projects

Automated Hygienic System Installation

Norwich, February 2021

View Project
Parcel Sortation System Extensions

Hampshire, July 2020

View Project
COVID-19 Critical Work Team

COVID-19 Critical Work Team, April 2020

View Project

What's New?